Jump to content

Log in or register to remove this advert

Penalties for ignoring RPA's?


Ledburyjosh
 Share

Recommended Posts

Log in or register to remove this advert

On 17/08/2022 at 21:24, Puffingbilly413 said:

My now far too cynical mind immediately comes to the conclusion that the contractors are well aware of the situation and what they can get away with.  Maybe a fine, maybe not.  But if a fine then just a cost of doing business.  See it all the time sadly.

That's pretty much it.

Link to comment
Share on other sites

On 17/08/2022 at 20:49, StephenMews said:

Another part of this to consider, is the damage enough to now cause complete tree failure and damage the now being built properties... Possibly yes, extensive damage? unlikey more garden sheds/fences etc..

If I am correct in thinking the LA choose to TPO the tree and prevent any work/removal they could be liable for any damage as is was foreseeable and preventable.

 

I shall upload an image to help show the scenario 

Not so. LA liability is for damage that is foreseeable. If risk is foreseeable and is serious and urgent then the exemption should be used. If it's less urgent an application should be made. Only on refusal is there any argument of LA liability, and even then an appeal should be considered.

But if failure arises from instability due to unaothrised excavatiions, the LA could comple the developer to reisntate the ground to make the tree stable. In my experience tthe excavatiin of roots close to a tree will only create risk either immediately duel to lack of lateral support or slowly due to infection and decay. In your scenario I think it could be very hard to hold a LA responsible for short term failure which could be prevented. The LA might be in no rush to allow removal if the demise of the tree could take years and years to develop.

Much lesser works than removal shoudl be considered first.

  • Like 1
Link to comment
Share on other sites

  • 1 year later...

Hi all 

 

I also need some advice on a similar topic- a planning permission has been granted for the structure to be built near a ash tree using piled solution- the floor level is approx 600mm lower then the rear garden, hence the ground must be lowered to achieve a level floor. The planning drawings show a level floor on plans and elevations which have been granted. The tree report states not to lower the ground. 
 

the contractor has dug down to the correct level to install the piled raft. The RPA witching the did is approx 8%, and only 3-4 roots were encountered. 
 

the conditions in the planning contradict each other - one condition states to follow the tree report which states do not lower ground level. And another states to match the approved drawing which clearly shows the the ground being lowered. 
 

as stated the contractor has already done the dig. I don’t think the tree will be affected as in my research  I have read maximum 20% root area can be damaged without damaging the tree, in this case it’s approx 8%.
 

I’m just not sure what the penalty is on a case like this, your help will be much appreciated 

Link to comment
Share on other sites

In light of the fact that UK LPA's have a Duty to make provision for the preservation of trees.... isn't it a shame that retained aged trees aren't TPO'd before planning consent is granted.

We've really got to pull our socks up. And perhaps start doing what is meaningful, rather than what is expedient.

DETAILS, DETAILS, DETAILS.

Link to comment
Share on other sites

19 hours ago, Engineeringalltheway said:

Hi all 

 

I also need some advice on a similar topic- a planning permission has been granted for the structure to be built near a ash tree using piled solution- the floor level is approx 600mm lower then the rear garden, hence the ground must be lowered to achieve a level floor. The planning drawings show a level floor on plans and elevations which have been granted. The tree report states not to lower the ground. 
 

the contractor has dug down to the correct level to install the piled raft. The RPA witching the did is approx 8%, and only 3-4 roots were encountered. 
 

the conditions in the planning contradict each other - one condition states to follow the tree report which states do not lower ground level. And another states to match the approved drawing which clearly shows the the ground being lowered. 
 

as stated the contractor has already done the dig. I don’t think the tree will be affected as in my research  I have read maximum 20% root area can be damaged without damaging the tree, in this case it’s approx 8%.
 

I’m just not sure what the penalty is on a case like this, your help will be much appreciated 

Hard to say what any penalties might be if the LPA has contradicted itself in the wording of the permission.

 

But the time to ask the question was probably some weeks ago...

Link to comment
Share on other sites

  • 3 weeks later...
On 15/09/2023 at 21:25, Engineeringalltheway said:

the conditions in the planning contradict each other - one condition states to follow the tree report which states do not lower ground level. And another states to match the approved drawing which clearly shows the the ground being lowered. 
 

as stated the contractor has already done the dig. I don’t think the tree will be affected as in my research  I have read maximum 20% root area can be damaged without damaging the tree, in this case it’s approx 8%.
 

I’m just not sure what the penalty is on a case like this, your help will be much appreciated 

If the conditions contradict each other then they don't meet the five tests for planning conditions as set out in National Planning Policy, that conditions should be:

  1.Necessary
        2.Relevant to planning 
        3.Relevant to the development permitted
        4.Enforceable
        5.Precise
        6.Reasonable in all other respects
 
It would therefore, in theory at least, be impossible for the LPA to take enforcement action on the contractor. The conflict in conditions needs to be pointed out to the case officer asap!
Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
 Share

  •  

  • Featured Adverts

About

Arbtalk.co.uk is a hub for the arboriculture industry in the UK.  
If you're just starting out and you need business, equipment, tech or training support you're in the right place.  If you've done it, made it, got a van load of oily t-shirts and have decided to give something back by sharing your knowledge or wisdom,  then you're welcome too.
If you would like to contribute to making this industry more effective and safe then welcome.
Just like a living tree, it'll always be a work in progress.
Please have a look around, sign up, share and contribute the best you have.

See you inside.

The Arbtalk Team

Follow us

Articles

×
×
  • Create New...

Important Information

We have placed cookies on your device to help make this website better. You can adjust your cookie settings, otherwise we'll assume you're okay to continue.