Can any of you folks recommend something that will capture progress of a 500kg load on a 2 to 1 haul system utilizing 10.5mm polyamide semi static that doesn't have any teeth and does have the option to safely lower off mid haul?

 

 

Thanks loads in advance.

 

Al.

Link to comment
Share on other sites

Log in or register to remove this advert

Can any of you folks recommend something that will capture progress of a 500kg load on a 2 to 1 haul system utilizing 10.5mm polyamide semi static that doesn't have any teeth and does have the option to safely lower off mid haul?

 

 

Thanks loads in advance.

 

Al.

 

this is going to be interesting, what you up to?

 

been thinking along similar lines for bat roost elevation replacment

Link to comment
Share on other sites

Prussic and pulley then i guess, cant think of owt else that would reliably release under load. Some sort of belay rack maybe, but that wouldnt be exactly hands off

 

Thanks mate but it really needs to be hands off and fairly friction free.

We intend to lift the load 100ft as quickly as possible using a speedboat.

Link to comment
Share on other sites

That is a tricky wicket, I think what you need is not a piece of kit but alot of cunning. I'm thinking something along the lines of using one device to perform in the progress capture department, then putting the rope in a lowering bollard/portawrap or what have you and finding some way to release the load of your capturing system so you can lower, possibly utilising a swinging bench and a number of tree climbers...

Edit: GRCS?

Link to comment
Share on other sites

That is a tricky wicket, I think what you need is not a piece of kit but alot of cunning. I'm thinking something along the lines of using one device to perform in the progress capture department, then putting the rope in a lowering bollard/portawrap or what have you and finding some way to release the load of your capturing system so you can lower, possibly utilising a swinging bench and a number of tree climbers...

Edit: GRCS?

 

I like the thought process.

bit concerned about having the load hang on the separate bit of progress capture. Like a Shunt or a Gibbs could handle the haul speed but I'd be worried about devices like that capturing the sheath once loaded but letting the core creep through until the resulting bulge jams the capture device.

A prusik would stop that from happening but theres no way to control it with the rope moving at speed on the haul and you'd probably have to cut it off in order to lower.

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
 Share

  •  

  • Featured Adverts

About

Arbtalk.co.uk is a hub for the arboriculture industry in the UK.  
If you're just starting out and you need business, equipment, tech or training support you're in the right place.  If you've done it, made it, got a van load of oily t-shirts and have decided to give something back by sharing your knowledge or wisdom,  then you're welcome too.
If you would like to contribute to making this industry more effective and safe then welcome.
Just like a living tree, it'll always be a work in progress.
Please have a look around, sign up, share and contribute the best you have.

See you inside.

The Arbtalk Team

Follow us

×
×
  • Create New...

Important Information

We have placed cookies on your device to help make this website better. You can adjust your cookie settings, otherwise we'll assume you're okay to continue.