I've got quite a big job coming off where there is a lot of electrickery invovoled, it's been agreed verbally. This is at a Guest House, so no room for error.

I've got a company to come in to do the electrical work for me. I could do it but I don't have the tickets to sign it off.

 

should I just put on the written quote that a third party is sorting out the electrics, or should I name them on the quote ?

 

Basically I'm trying to distance myself from any of the electrical work. Am I pi55ing in the wind or is this possible, remembering I will be the main contractor.

Link to comment
Share on other sites

Log in or register to remove this advert

Can you not cover this in terms and conditions? As in third party contractors may be used on a bonafide contractor basis and will therefore be totally responsible for their work.  As long as all three parties have a written understanding/contract surely that would cover it. I'd think you then don't appear to be palming off responsibility but come across as a capable project manager. 

Link to comment
Share on other sites

I've got quite a big job coming off where there is a lot of electrickery invovoled, it's been agreed verbally. This is at a Guest House, so no room for error.
I've got a company to come in to do the electrical work for me. I could do it but I don't have the tickets to sign it off.
 
should I just put on the written quote that a third party is sorting out the electrics, or should I name them on the quote ?
 
Basically I'm trying to distance myself from any of the electrical work. Am I pi55ing in the wind or is this possible, remembering I will be the main contractor.

Mention it in the method statement


Sent from my iPhone using Arbtalk
Link to comment
Share on other sites

If you are pricing the whole job you are responsible for the non-performance of any subcontractor .In law there is privity of  contract, this means that the client has a contract with you and not the subcontractor the only way to remove this risk is to have the client split the work into two contracts and have it priced accordingly.

Clauses in method statements or term & conditions will not absolve you of any non-performance.

Edited by Stock
  • Like 1
Link to comment
Share on other sites

16 hours ago, Mull said:

If you want to be "main contractor" you have to accept the sh1te! 

Why bother? 

Let the sparkie do his own thing and don't lose sleep over being the "main man"!

You are right, for once.......

 

Greed was getting the better of me, I could have earned more money by putting 'a bit' on top of the sparkys bill.

 

its been agreed that I will do the ground work, install pipework, sump, and put pumps in place and the sparky will do his bit after.

 

thanks for the replies folks.

Link to comment
Share on other sites

2 hours ago, eggsarascal said:

You are right, for once.......

 

Greed was getting the better of me, I could have earned more money by putting 'a bit' on top of the sparkys bill.

 

its been agreed that I will do the ground work, install pipework, sump, and put pumps in place and the sparky will do his bit after.

 

thanks for the replies folks.

What do you mean "for once"??????????

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
 Share

  •  

  • Featured Adverts

About

Arbtalk.co.uk is a hub for the arboriculture industry in the UK.  
If you're just starting out and you need business, equipment, tech or training support you're in the right place.  If you've done it, made it, got a van load of oily t-shirts and have decided to give something back by sharing your knowledge or wisdom,  then you're welcome too.
If you would like to contribute to making this industry more effective and safe then welcome.
Just like a living tree, it'll always be a work in progress.
Please have a look around, sign up, share and contribute the best you have.

See you inside.

The Arbtalk Team

Follow us

×
×
  • Create New...

Important Information

We have placed cookies on your device to help make this website better. You can adjust your cookie settings, otherwise we'll assume you're okay to continue.